First page Back Continue Last page Overview Graphics
Huron & Croke Reconstruction
Current Overall Budget
- 2006 Carryover $529,265
- 2007 Budget $2,095,503
- 2007 Anticipated $750,500
- 2008 Proposed $3,367,927
- Total Current Funding $6,750,195
Projected Need by Phases
- 104th - Naiad $1,500,000
- Naiad - Kennedy $5,100,000
- Huron St. $3,200,000
- Basic Shoreline $735,700
- Shoreline Enhancements $1,164,300
- Kennedy – 112th $3,450,000
Total Projected Need $10,050,000 (20% Contingency)
Current Funding Gap ($3,299,805)