Implementation
Schedule
December 2007 - January 2008: Prepare design plans and specifications
February 2008: Submit plans for State review and approval
March – April 2008: Construction/equipment installation
May 2008: Chemical feed system at Lift Station A on-line
Summer 2008: Conduct additional pilot studies
Spring 2009: Implement permanent odor control system and optimize operations