2007 Activities
September - December
September 28 – Submitted site amendment applications for chemical feed facilities at Lift Station A and Bunker Hill
October 9 – Webster Environmental, Inc. final report
October 12 – Cease bi-weekly shock dosing of sodium hydroxide
October 15 – Began 3-week Calcium Nitrate (Bioxide) pilot study
October 18 – Odor control implementation flow chart to State
October 24 – State approves site amendment applications for the WWTP, Bunker Hill Lift Station, and Lift Station A
November 2 – Concluded 3-week Calcium Nitrate (Bioxide) pilot
November 26 – Cost estimate from Carollo Engineering to design chemical feed system (Lift Station A and WWTP)